Dubai Electricity and Water Authority (DEWA) has announced that its total investment in electricity transmission projects has now surpassed AED 7.6 billion.

The milestone includes the commissioning of four 132 kV substations during H1 2025, adding 450 MVA in capacity and extending 228 km of transmission cables across the emirate.

HE Saeed Mohammed Al Tayer, MD & CEO of DEWA, stated that the expansion is aligned with Dubai’s economic and social agendas and aims to meet the emirate’s growing electricity demand. He confirmed that 49 new 132 kV substations and two 400 kV substations are currently under construction, with additional tenders planned for 57 more 132 kV substations and 160 km of underground cable extensions over the next three years.

The total number of transmission substations in Dubai reached 391 by the end of H1 2025, comprising 27 at 400 kV and 364 at 132 kV. Notably, new substations were completed in Al Yalayis 5, Hatta, and Warsan 4, serving both new housing projects and rural regions.

The projects have been implemented using advanced digital technologies and over 4.5 million working hours. DEWA has also awarded new contracts worth AED 1.1 billion to build 10 additional 132 kV substations across areas like Al Barsha South 2, Business Bay, and Dubai Silicon Oasis, as well as cable extensions worth AED 288 million.

News Source: Dubai Media Office

Ad
Ad
Ummulkiram Pardawala

Written by Ummulkiram Pardawala

Ummulkiram is a Content Writer at HiDubai. She holds a Bachelors Degree in Finance, is an expert Baker, and also a wordsmith.
Ad
Dark Light